The invention provides an injection moulding equipment, including a mould core and a driving device, in which the mould core includes a mould upper shell with an injection space, a mould lower shell matched with the mould upper shell, a cavity through hole on the lower shell of the mould, and a conversion core arranged in the cavity through hole; and the driving device includes a power source assembly, a connecting guide rail and a core connecting group. The power source assembly includes the main part of the power source and the driving rod, the first end of the connecting rail is fixed to the end of the driving rod, the first end of the core connecting component is connected to the conversion core, and the second end of the core connecting component reaches the top and the bottom of the conversion slot. The injection moulding equipment based on this technical scheme can solve the technical problems existing in the prior technology that the first injection material and the second injection material can not be poured into the same mould equipment in turn, resulting in high cost of the mould equipment, cumbersome production process and low production efficiency.
【技术实现步骤摘要】
注塑成型设备
本专利技术属于注塑工装
,更具体地说,是涉及一种注塑成型设备。
技术介绍
为了获得注塑件的优异使用性能,越来越多的注塑件采用双层材料结合注塑成型,通过两层不同材料达到不同的功能作用,并且使两层材料所达到的功能作用相互结合,使得注塑件具备了单种材料注塑成型的同种注塑件所无法具有的优异使用性能。但是,现有技术在进行双层材料结合注塑成型的加工过程中,针对一种材料的注塑成型就需要专门制备使用一套模具设备,也就是说,注塑生产完成一件双层材料的注塑件至少需要使用两套模具设备相结合,在其中一套模具设备中注塑成型其中一种材料的注塑半成品之后,再将该半成品转移至另一套设备中进行另一种材料的注塑成型,从而获得完成的双层材料结合注塑成型的成品注塑件。为了改进现有技术的制备加工方式,以实现使用一套模具即可完成双层材料结合注塑成型所需的双层材料注塑件,这就需药改变模具型芯的结构形式,使得能够在同一套模具型芯中相应地形成注塑两种注塑材料所需的注塑腔。显然,对两种注塑材料进行注塑的过程必须分开而无法同时进行注塑,这就需要对模具型芯所形成的注塑腔进行转换,使得在注塑成型完成一种注塑材料之后进行转换形成第二种注塑材料所需的注塑腔。也就是说,现有技术在生产制备双层材料结合的注塑件产品过程中,无法实现在同一模具设备中依次浇注成型第一种注塑材料和第二种注塑材料,导致现有技术的生产制备过程中的模具设备成本高、生产制备工序繁琐、生产效率低的缺陷。
技术实现思路
本专利技术的目的在于提供一种注塑成型设备,以解决现有技术中存在的无法实现在同一模具设备中依次浇注成型第一种注塑材料和第二种注 ...
【技术保护点】
1.一种注塑成型设备,包括模具型芯(100)和驱动装置(200),其特征在于,所述模具型芯(100)包括:模具上壳(110),所述模具上壳(110)设有注塑空间(111);模具下壳(120),所述模具下壳(120)与所述模具上壳(110)配合合模,所述模具下壳(120)上设有型腔通孔(121),所述型腔通孔(121)与所述注塑空间(111)正对设置;转换型芯(130),所述转换型芯(130)设置于所述型腔通孔(121)内,所述转换型芯(130)可沿所述型腔通孔(121)的轴线方向滑移,且所述转换型芯(130)的侧面与所述型腔通孔(121)的孔壁相接触;其中,所述转换型芯(130)具有第一工位和第二工位,当所述转换型芯(130)位于所述第一工位时,所述注塑空间(111)的开口端抵顶于所述转换型芯(130)的上表面以形成第一注塑腔,当所述转换型芯(130)位于所述第二工位时,所述转换型芯(130)的上表面、所述型腔通孔(121)的壁面以及所述注塑空间(111)的开口端的端面形成第二注塑腔;所述驱动装置(200)包括:动力源组件(210),所述动力源组件(210)包括动力源本体部(211)和 ...
【技术特征摘要】
1.一种注塑成型设备,包括模具型芯(100)和驱动装置(200),其特征在于,所述模具型芯(100)包括:模具上壳(110),所述模具上壳(110)设有注塑空间(111);模具下壳(120),所述模具下壳(120)与所述模具上壳(110)配合合模,所述模具下壳(120)上设有型腔通孔(121),所述型腔通孔(121)与所述注塑空间(111)正对设置;转换型芯(130),所述转换型芯(130)设置于所述型腔通孔(121)内,所述转换型芯(130)可沿所述型腔通孔(121)的轴线方向滑移,且所述转换型芯(130)的侧面与所述型腔通孔(121)的孔壁相接触;其中,所述转换型芯(130)具有第一工位和第二工位,当所述转换型芯(130)位于所述第一工位时,所述注塑空间(111)的开口端抵顶于所述转换型芯(130)的上表面以形成第一注塑腔,当所述转换型芯(130)位于所述第二工位时,所述转换型芯(130)的上表面、所述型腔通孔(121)的壁面以及所述注塑空间(111)的开口端的端面形成第二注塑腔;所述驱动装置(200)包括:动力源组件(210),所述动力源组件(210)包括动力源本体部(211)和驱动杆(212),所述动力源本体部(211)与所述驱动杆(212)驱动连接,且所述动力源本体部(211)驱动所述驱动杆(212)沿自身中心轴线方向伸缩移动;连接导轨(220),所述连接导轨(220)的第一端与所述驱动杆(212)的端部固定连接,所述连接导轨(220)上设有转换工位槽(221),所述转换工位槽(221)的底面具有高度不同的第一承载工位(2211)和第二承载工位(2212),且所述第一承载工位(2211)与所述第二承载工位(2212)之间平滑过渡;型芯连接组件(230),所述型芯连接组件(230)的第一端与所述转换型芯(130)连接,所述型芯连接组件(230)的第二端抵顶与所述转换工位槽(221)的底面上,当所述转换型芯(130)位于所述第一工位时,所述型芯连接组件(230)的第二端位于所述第一承载工位(2211)上,当所述转换型芯(130)位于所述第二工位时,所述型芯连接组件(230)的第二端位于所述第二承载工位(2212)上。2.如权利要求1所述的注塑成型设备,其特征在于,所述模具型芯(100)还包括第一辅助组件(141)和第二辅助组件(142),所述第一辅助组件(141)与第二辅助组件(142)相对地安装于所述第一注塑腔的两侧。3.如权利要求2所述的注塑成型设备,其特征在于,所述第一辅助组件(141)包括第一辅助安装块(1411)和第一型位杆(1412),所述第一辅助安装块(1411)固定安装于所述模具上壳(110)与所述模具下壳(120)之间,所述第一辅助安装块(1411)上设有第一安装孔,所述第一型位杆(1412)插设于所述第一安装孔内,且所述第一型位杆(1412)的端部延伸至所述第一注塑腔;所述第二辅助组件(142)包括第二辅助安装块(1421)和第二型位杆(1422),所述第二辅助安装块(1421)固定安装于所述模具上壳(110)与所述模具下壳(120)之间,所述第二辅助安装块(1421)上设有第二安装孔,所述第二型位杆(1422)插设于所述第二安装孔内,且所述第二型位杆(1422)的端部延伸至所述第一注塑腔,所述第二型位杆(1422)与所述第一型...
【专利技术属性】
技术研发人员:韦俊军,林立,黎猛,李飞,
申请(专利权)人:深圳市银宝山新科技股份有限公司,
类型:发明
国别省市:广东,44