The invention relates to a pad sleeving device for road and bridge construction, which comprises a guide material pipe, a guide material pipe arranged vertically and the lower end constitutes an outlet, a baffle is rotated on both sides of the guide material pipe, a cantilever end of the baffle extends into the tube cavity of the guide material pipe, two bottom plates of the support block are opposed to the overhanging end of the baffle, a push mechanism is arranged on the guide material pipe, and a push mechanism driver is arranged on the push mechanism. Material guide moves to the lower pipe orifice, and the cross section of the guide tube coincides with the outer outline of the support block, thus realizing the position limitation of the cushion block. When the cushion is derived from the lower pipe orifice of the guide tube, the cross section size of the guide tube is slightly larger than the cross section size of the support block of the cushion block, thus ensuring the normal fall of the cushion block, and under the blocking effect of the baffle, realizing the cushion block. When the system moves to the upper end of the pre-embedded bolt, the push mechanism starts and the baffle is separated from the lower end of the support block, thus pushing the pad onto the pre-embedded bolt.
【技术实现步骤摘要】
路桥施工用垫块穿套装置
本专利技术涉及工程施工
,具体涉及一种路桥施工用垫块穿套装置。
技术介绍
桥梁实施施工后,在桥梁的两侧需要铺设路肩石,路肩石沿着桥梁的长度方向相互挨着排列,现有技术中,路肩石通过运输设备运输至桥梁上,桥梁在施工时,预先在桥梁的两侧预留用于固定路肩石的预埋螺栓或者水泥卡槽,路肩石运输过来后,通过人工转运路肩石的方式将路肩石沿着桥梁长度方向摆放,而后通过人工的方式将路肩石搬运至路肩石的安装位,从而实现对路肩石的固定,上述通过人工安装路肩石的方式不但效率低下,而且路肩石的上端面高度很难与桥梁的起伏保持一致,从而使得路肩石施工经常与设计标准不符,导致返工的问题。为实现对路肩石铺设时高度调整,采用预留螺栓与调节螺母的方式进行调整,而路肩石重量较大,为实现对路肩石的稳定支撑,采用在预留螺栓上套设垫块的方式,利用垫块实现对路肩石的支撑,而如何将垫块有效的穿套在垫块上,对于整个路桥路肩石的铺设尤为关键。
技术实现思路
本专利技术的目的是:提供一种路桥施工用垫块穿套装置,能够将垫块套装在预留螺栓上。为实现上述目的,本专利技术采用的技术方案是:路桥施工用垫块穿套装置,包括导向料管,所述导向料管竖直布置且下端构成出料口,所述导向料管的下端两侧转动式设置有挡板,所述挡板的转动轴芯线水平且与水泥预料槽长度方向垂直,所述挡板的悬伸端伸入导向料管的管腔,所述支撑块的两端下板面与挡板的悬伸端抵靠,所述导向料管上设置有推送机构,推送机构驱动物料向导向料管下管口移动。与现有技术相比,本专利技术具备的技术效果为:导向料管的截面与支撑块的外轮廓吻合,从而实现对垫块姿态的 ...
【技术保护点】
1.路桥施工用垫块穿套装置,其特征在于:包括导向料管(81),所述导向料管(81)竖直布置且下端构成出料口,所述导向料管(811)的下端两侧转动式设置有挡板(82),所述挡板(82)的转动轴芯线水平且与水泥预料槽(30)长度方向垂直,所述挡板(82)的悬伸端伸入导向料管(81)的管腔,所述支撑块(921)的两端下板面与挡板(82)的悬伸端抵靠,所述导向料管(81)上设置有推送机构,推送机构驱动物料向导向料管(81)下管口移动。
【技术特征摘要】
1.路桥施工用垫块穿套装置,其特征在于:包括导向料管(81),所述导向料管(81)竖直布置且下端构成出料口,所述导向料管(811)的下端两侧转动式设置有挡板(82),所述挡板(82)的转动轴芯线水平且与水泥预料槽(30)长度方向垂直,所述挡板(82)的悬伸端伸入导向料管(81)的管腔,所述支撑块(921)的两端下板面与挡板(82)的悬伸端抵靠,所述导向料管(81)上设置有推送机构,推送机构驱动物料向导向料管(81)下管口移动。2.根据权利要求1所述的路桥施工用垫块穿套装置,其特征在于:所述导向料管(81)内设置有限位杆(831),所述限位杆(831)竖直布置,所述限位杆(83)伸入圆弧形缺口(922)内,所述导向料管(81)的截面整体为矩形,所述支撑块(92)的两端与导向料管(81)的管壁靠近,所述限位杆(83)的上端设置成尖端。3.根据权利要求1所述的路桥施工用垫块穿套装置,其特征在于:所述导向料管(81)的外壁两侧均设置有条形开口(811),所述条形开口(811)竖直布置且设置有驱动条带(851),所述驱动条带(85)竖直布置且伸入条形开口(811)内,所述驱动条带(85)与支撑块(92)的两端抵靠或分离。4.根据权利要求1所述的路桥施工用垫块穿套装置,其特征在于:所述挡板(82)的一端转动式设置有横杆(821),所述横杆(821)上套设有弹性扭簧(822),所述弹性扭簧(822)的两端分别与横杆(821)及挡板(82)连接。5.根据权利要求1所述的路桥施工用垫块穿套装置,其特征在于:所述驱动条带(85)为封闭式履带且转动式设置在安装支架(851)上,所述安装支架(851)的上端滑动设置有第一、第二支撑滑杆(852、853),所述第一、第二支撑滑杆(852、853)的长度方向水平且与水泥预料槽(30)长度方向平行,所述第一支撑滑杆(852)上套设有弹簧(85211),所述弹簧(8521)的两端分别与安装支架(851)抵靠,所述安装支架(851)上分别设置有滚珠(8511),所述安装支架(851)的旁侧设置有驱动板(854),所述驱动板(854)...
【专利技术属性】
技术研发人员:朱晓鑫,
申请(专利权)人:安徽企路石工程技术开发有限公司,
类型:发明
国别省市:安徽,34