The invention relates to a construction method of a silt deep foundation pit, belonging to the field of building construction, with the purpose of reducing the construction cost of the foundation pit and improving the construction safety. The method is as follows: in the foundation pit into fixed pile in fixed pile top crown beam is arranged at the lower end can move in the top beam suspension bridge crane with lifting worktable, suspension arranged on the working table lines; excavation, first into a block of steel formwork in the adjacent fixed pile from top to bottom, and the excavation of a a steel formwork height, then fixed in the adjacent pile driving a piece of steel formwork, steel formwork and top pressure before running down a piece of steel template distance, connecting the upper and lower two adjacent steel template, and then repeat the operation to the foundation pit excavation; excavation completed. The present invention, the supporting structure is simple, easy and safe operation, less material consumption, reduces the risk of retaining structure of excavator touch support, ensure the foundation pit forming quality; eliminate the excavator was buried in mud hidden danger, high safety and convenient operation can accelerate the construction progress.
【技术实现步骤摘要】
淤泥深基坑施工方法
本专利技术属于建筑施工领域,具体的是淤泥深基坑施工方法。
技术介绍
对于淤泥土质深基坑的开挖,通常首先采用基坑围护桩,如钢板桩、钻孔灌柱桩或地下连续墙等进行支护,然后再利用挖土机开挖。但是,以上支护方法材料耗用量大,且在深基坑中停置使用挖土机易被淤泥淹埋,施工成本高且有安全隐患,给施工带来很多难题。
技术实现思路
本专利技术所要解决的技术问题是提供一种淤泥深基坑施工方法,以降低基坑施工成本,并提高施工安全性。本专利技术采用的技术方案是:淤泥深基坑施工方法,包括顺序进行的以下步骤:步骤一、在基坑周边打入固定桩至老土层,在固定桩顶部设置冠梁将固定桩连成一体,并在基坑边口设有砼护边;步骤二、降低地下水位;步骤三、在冠梁安装可移动的桥式吊车,在桥式吊车的下端通过吊装柱吊装有悬置工作台,在悬置工作台上设置挖土机;步骤四、挖土机进行开挖:首先在相邻固定桩间由上至下沿设置于固定桩上的限位结构打入一块钢模板,然后开挖一个钢模板的高度,接着在相邻固定桩间由上至下打入后一块钢模板,后一块钢模板顶压之前的钢模板向下运行一节钢模板高度的距离,将上下相邻两块钢模板可拆卸连接,接着开挖一个钢模板的高度;重复该操作至基坑开挖完成;步骤五、拆除支护。进一步的,在基坑两侧的冠梁上安装有与桥式吊车滑动配合的行车轨道。进一步的,在冠梁设置结速后,在土方开挖前,安装直撑和斜撑;所述直撑两端分别与基坑对侧的固定桩的内侧相连,所述斜撑两端分别与基坑相邻两侧的固定桩的内侧相连;且直撑和斜撑均位于固定桩的顶部。进一步的,所述限位结构为设置于固定桩两侧的与钢模板的厚度相适配的插槽,所述插槽 ...
【技术保护点】
淤泥深基坑施工方法,其特征在于:包括顺序进行的以下步骤:步骤一、在基坑(1)周边打入固定桩(2)至老土层,在固定桩(2)顶部设置冠梁(4)将固定桩(2)连成一体,并在基坑(1)边口设有砼护边(3);步骤二、降低地下水位;步骤三、在冠梁(4)安装可移动的桥式吊车(8),在桥式吊车(8)的下端通过吊装柱(22)吊装有悬置工作台(9),在悬置工作台(9)上设置挖土机(10);步骤四、挖土机(10)进行开挖:首先在相邻固定桩(2)间由上至下沿设置于固定桩(2)上的限位结构打入一块钢模板(11),然后开挖一个钢模板(11)的高度,接着在相邻固定桩(2)间由上至下打入后一块钢模板(11),后一块钢模板(11)顶压之前的钢模板(11)向下运行一节钢模板(11)高度的距离,将上下相邻两块钢模板(11)可拆卸连接,接着开挖一个钢模板(11)的高度;重复该操作至基坑(1)开挖完成;步骤五、拆除支护。
【技术特征摘要】
1.淤泥深基坑施工方法,其特征在于:包括顺序进行的以下步骤:步骤一、在基坑(1)周边打入固定桩(2)至老土层,在固定桩(2)顶部设置冠梁(4)将固定桩(2)连成一体,并在基坑(1)边口设有砼护边(3);步骤二、降低地下水位;步骤三、在冠梁(4)安装可移动的桥式吊车(8),在桥式吊车(8)的下端通过吊装柱(22)吊装有悬置工作台(9),在悬置工作台(9)上设置挖土机(10);步骤四、挖土机(10)进行开挖:首先在相邻固定桩(2)间由上至下沿设置于固定桩(2)上的限位结构打入一块钢模板(11),然后开挖一个钢模板(11)的高度,接着在相邻固定桩(2)间由上至下打入后一块钢模板(11),后一块钢模板(11)顶压之前的钢模板(11)向下运行一节钢模板(11)高度的距离,将上下相邻两块钢模板(11)可拆卸连接,接着开挖一个钢模板(11)的高度;重复该操作至基坑(1)开挖完成;步骤五、拆除支护。2.如权利要求1所述的淤泥深基坑施工方法,其特征在于:在基坑(1)两侧的冠梁(4)上安装有与桥式吊车(8)滑动配合的行车轨道(5)。3.如权利要求1所述的淤泥深基坑施工方法,其特征在于:在冠梁(4)设置结速后,在土方开挖前,安装直撑(6)和斜撑(7);所述直撑(6)两端分别与基坑(1)对侧的固定桩(2)的内侧相连,所述斜撑(7)两端分别与基坑(1)相邻两侧的固定桩(2)的内侧相连;且直撑(6)和斜撑(7)均位于固定桩(2)的顶部。4.如权利要求1所述的淤泥深基坑施工方法,其特征在于:所述限位结构...
【专利技术属性】
技术研发人员:杨贵柏,马会军,范华猛,梁超,
申请(专利权)人:中国十九冶集团有限公司,
类型:发明
国别省市:四川,51